OpenAid Ledger

What changed inside the files

Every project-level change the ledger has found by comparing consecutive versions of the same file: budgets rewritten, transactions removed, end dates moved, projects that disappeared.

  1. 2026-10-04
    Transactions removed
    +1 more

    For the project "Privatization & Utility Sector Reform (44000-P050439)", the budget increased by 75.50% from USD 45,585,438.91 to USD 80,021,368.43, and 162 transactions totaling USD 49,084,742.00 were removed and replaced

    • Transactions removed: 162 transactions removed, USD 49.08m
    • Budget changed: Budget USD 45.59m → USD 80.02m (+75.5%)

    Privatization & Utility Sector Reform · The World Bank · compare 04c8ff56 → ab0d64d2

  2. 2026-10-04
    Transactions removed

    For the World Bank project "Second Environmental Management and Capacity Building Project (44000-P073089)", 231 transactions totaling USD 64,421,497.00 were removed, as part of a likely bulk correction across 19 projects.

    • Transactions removed: 231 transactions removed, USD 64.42m

    Second Environmental Management and Capacity Building Project · The World Bank · compare 04c8ff56 → ab0d64d2

  3. 2026-10-04
    Transactions removed
    +1 more

    For the World Bank project "Uganda Ninth Poverty Reduction Support Credit (44000-P097325)", 35 transactions totaling 183,238,782.00 USD were removed and the budget increased by 1.30% from 200,000,000.00 USD to 202,657,856.00 USD

    • Transactions removed: 35 transactions removed, USD 183.24m
    • Budget changed: Budget USD 200.00m → USD 202.66m (+1.3%)

    Uganda Ninth Poverty Reduction Support Credit · The World Bank · compare 04c8ff56 → ab0d64d2

  4. 2026-10-04
    Transactions removed
    +1 more

    For "Preparedness and Control of Avian Influenza (44000-P110207)", the budget increased by 16.00% to USD 23,004,540.87, and 66 transactions totaling USD 15,259,541.00 were removed. This is likely part of a bulk correction by the publisher.

    • Transactions removed: 66 transactions removed, USD 15.26m
    • Budget changed: Budget USD 19.83m → USD 23.00m (+16.0%)

    Preparedness and Control of Avian Influenza · The World Bank · compare 04c8ff56 → ab0d64d2

  5. 2026-10-04
    Transactions removed

    In "Uganda: Energy for Rural Transformation APL-2 (44000-P112334)", 137 transactions totaling 148,156,008.00 USD were removed and another 137 transactions totaling 148,156,008.00 USD were added, with money unchanged; this update is likely part of a bulk correction affecting 19

    • Transactions removed: 137 transactions removed, USD 148.16m

    Uganda: Energy for Rural Transformation APL-2 · The World Bank · compare 04c8ff56 → ab0d64d2

  6. 2026-10-04
    Transactions removed

    In project "Competitiveness and Enterprise Development Project (CEDP) (44000-P130471)", 84 transactions totaling 357,081,780.00 USD were removed and 84 transactions totaling 357,081,780.00 USD were added, with money unchanged; this is likely part of a bulk correction.

    • Transactions removed: 84 transactions removed, USD 357.08m

    Competitiveness and Enterprise Development Project (CEDP) · The World Bank · compare 04c8ff56 → ab0d64d2

  7. 2026-10-04
    Transactions removed

    For the project "Uganda: Albertine Region Sustainable Development Project (44000-P145101)", 47 transactions totaling 265,312,507.00 USD were removed and another 47 transactions totaling 265,312,507.00 USD were added, meaning the total monetary value is unchanged. This is likely part of a bulk correction affecting 1

    • Transactions removed: 47 transactions removed, USD 265.31m

    Uganda: Albertine Region Sustainable Development Project · The World Bank · compare 04c8ff56 → ab0d64d2

  8. 2026-10-04
    Transactions removed

    For the "Skills Development Project (44000-P145309)", 50 transactions totaling USD 177,321,489.00 were removed and replaced with 50 newly added transactions totaling USD 177,321,489.00, with money unchanged; this is likely part of a bulk correction of 19 projects.

    • Transactions removed: 50 transactions removed, USD 177.32m

    Skills Development Project · The World Bank · compare 04c8ff56 → ab0d64d2

  9. 2026-10-04
    Transactions removed

    For project "Uganda Intergovernmental Fiscal Transfers Program (44000-P160250)", 45 transactions totaling USD 957,436,465.00 were removed and replaced, budget periods were updated with the total budget unchanged, and organization identifiers were modified. This is likely part of a bulk correction across 19 projects.

    • Transactions removed: 45 transactions removed, USD 957.44m

    Uganda Intergovernmental Fiscal Transfers Program · The World Bank · compare 04c8ff56 → ab0d64d2

  10. 2026-10-04
    Transactions removed

    For the "Integrated Water Management and Development Project (44000-P163782)", 59 transactions totaling 557,385,515.00 USD were replaced, with money unchanged; this is part of a bulk correction of 19 projects in the same file update.

    • Transactions removed: 59 transactions removed, USD 557.39m

    Integrated Water Management and Development Project · The World Bank · compare 04c8ff56 → ab0d64d2

  11. 2026-10-04
    Transaction rewritten
    +1 more

    For the "Electricity Access Scale-up Project (EASP) (44000-P166685)", an August 31, 2024 transaction value changed from USD 10,575,586.00 to USD 39,797,423.00, while money was unchanged for three other transactions; this is part of a bulk correction across 19 projects

    • Transaction rewritten: Transaction on 2024-08-31 rewritten USD 10,575,586 → USD 39,797,423
    • Transaction rewritten: Transaction on 2024-08-31 rewritten USD 39,797,423 → USD 10,575,586

    Electricity Access Scale-up Project (EASP) · The World Bank · compare 04c8ff56 → ab0d64d2

  12. 2026-10-04
    Transactions removed

    For the "Uganda Investing in Forests and Protected Areas for Climate-Smart Development Project (44000-P170466)", 40 transactions totaling USD 220,747,231.00 were removed and replaced with 40 new transactions totaling USD 220,747,231.00, with money unchanged; this is likely part of a bulk correction.

    • Transactions removed: 40 transactions removed, USD 220.75m

    Uganda Investing in Forests and Protected Areas for Climate-Smart Development Project · The World Bank · compare 04c8ff56 → ab0d64d2

  13. 2026-10-04
    Transactions removed

    For the "Uganda Digital Acceleration Project - GovNet (44000-P171305)", 24 transactions totaling USD 247,280,536.00 were removed and replaced with 24 newly added transactions totaling USD 247,280,536.00, with money unchanged; this is part of a bulk correction of 19 projects.

    • Transactions removed: 24 transactions removed, USD 247.28m

    Uganda Digital Acceleration Project - GovNet · The World Bank · compare 04c8ff56 → ab0d64d2

  14. 2026-10-04
    Transactions removed
    +1 more

    For the project "Uganda: Investment for Industrial Transformation and Employment (44000-P171607)", the budget increased by 111.00% to USD 566,427,000.02, alongside four transactions being removed and re-added with receiver names, and organization and identifier updates, as part of a bulk correction.

    • Transactions removed: 4 transactions removed, USD 251.03m
    • Budget changed: Budget USD 268.48m → USD 566.43m (+111.0%)

    Uganda: Investment for Industrial Transformation and Employment · The World Bank · compare 04c8ff56 → ab0d64d2

  15. 2026-10-04
    Transactions removed

    For the World Bank project "Uganda COVID-19 Economic Crisis and Recovery Development Policy Financing (44000-P173906)", 14 transactions totaling USD 591,526,391.00 were removed and re-added with receiver names, two budget periods totaling USD 600,000,000.00 ending on 2021-06-

    • Transactions removed: 14 transactions removed, USD 591.53m

    Uganda COVID-19 Economic Crisis and Recovery Development Policy Financing · The World Bank · compare 04c8ff56 → ab0d64d2

  16. 2026-10-04
    Transactions removed

    In the "Uganda COVID-19 Response and Emergency Preparedness Project (44000-P174041)", 37 transactions totaling USD 340,723,937.00 were replaced and organizations were updated, while the total money was unchanged; this is part of a bulk correction affecting 19 projects.

    • Transactions removed: 37 transactions removed, USD 340.72m

    Uganda COVID-19 Response and Emergency Preparedness Project · The World Bank · compare 04c8ff56 → ab0d64d2

  17. 2026-10-04
    Transactions removed

    For "Northern Uganda Social Action Fund IV Project (44000-P179904)", two transactions totaling USD 294,146,506.00 were updated on 2025-04-30 and 2026-06-30 to include the Inspectorate of Government alongside the Office of the Prime Minister, with total money unchanged. As this project is one of

    • Transactions removed: 2 transactions removed, USD 294.15m

    Northern Uganda Social Action Fund IV Project · The World Bank · compare 04c8ff56 → ab0d64d2

  18. 2026-10-04
    Transactions removed

    For project "Uganda Development Response to Displacement Impacts Project Phase II (44000-P510476)", two transactions totaling USD 328,000,000.00 dated June 30, 2025, were removed and re-added with the Inspectorate of Government added as a receiver, with the total money unchanged; this is likely part of a bulk correction.

    • Transactions removed: 2 transactions removed, USD 328.00m

    Uganda Development Response to Displacement Impacts Project Phase II · The World Bank · compare 04c8ff56 → ab0d64d2

  19. 2026-10-04
    Transactions removed

    For project "Uganda Strengthening Public Investment and Asset Management for Growth and Resilience Operation (PIM Plus) (44000-P511206)", two transactions totaling USD 208,000,000.00 were removed and replaced with two identical transactions adding the Ministry of Finance, Planning & Economic Development as a receiver alongside the National Planning Authority, with money unchanged; this is one of 19 projects with material

    • Transactions removed: 2 transactions removed, USD 208.00m

    Uganda Strengthening Public Investment and Asset Management for Growth and Resilience Operation (PIM Plus) · The World Bank · compare 04c8ff56 → ab0d64d2

  20. 2026-10-04
    Transactions removed
    +1 more

    For project "Second Basic Education (44000-P107845)", the budget increased by 10.10% to 55,430,573.56 USD from 50,333,333.34 USD, and 71 transactions totaling 43,762,663.00 USD were removed. This change is likely part of a

    • Transactions removed: 71 transactions removed, USD 43.76m
    • Budget changed: Budget USD 50.33m → USD 55.43m (+10.1%)

    Second Basic Education · The World Bank · compare 5c90b544 → bc237372

  21. 2026-10-04
    Transactions removed
    +1 more

    In "Ferghana Valley Water Resources Management Phase-I Project", the budget increased by 38.80% (from USD 86,314,224.72 to USD 119,766,072.28), 103 transactions totaling USD 89,346,151.00 were removed and re-added, and organizations were updated. This update is

    • Transactions removed: 103 transactions removed, USD 89.35m
    • Budget changed: Budget USD 86.31m → USD 119.77m (+38.8%)

    Ferghana Valley Water Resources Management Phase-I Project · The World Bank · compare 5c90b544 → bc237372

  22. 2026-10-04
    Transaction rewritten
    +5 more

    For the project "Uzbekistan Bukhara and Samarkand Sewerage Project (44000-P112719)", commitment cancellations on 2020-03-31 changed from USD -5,611,784.00 to USD -9,388,148.00, alongside three disbursement transaction updates, as part of a bulk correction across multiple projects.

    • Transaction rewritten: Transaction on 2020-03-31 rewritten USD -9,388,148 → USD -5,611,784
    • Transaction rewritten: Transaction on 2019-05-31 rewritten USD 1,362,654 → USD 187,248
    • Transaction rewritten: Transaction on 2019-05-31 rewritten USD 187,248 → USD 1,362,654
    • Transaction rewritten: Transaction on 2019-06-30 rewritten USD 2,530,833 → USD 69,489
    • Transaction rewritten: Transaction on 2020-03-31 rewritten USD -5,611,784 → USD -9,388,148
    • Transaction rewritten: Transaction on 2019-06-30 rewritten USD 69,489 → USD 2,530,833

    Uzbekistan Bukhara and Samarkand Sewerage Project · The World Bank · compare 5c90b544 → bc237372

  23. 2026-10-04
    Transactions removed

    For the project "Energy Efficiency Facility for Industrial Enterprises (44000-P118737)", 220 transactions totaling 496,377,196.00 USD were removed and another 220 transactions totaling 496,377,196.00 USD were added, with the total monetary value unchanged; this is part of a bulk correction affecting 18 projects.

    • Transactions removed: 220 transactions removed, USD 496.38m

    Energy Efficiency Facility for Industrial Enterprises · The World Bank · compare 5c90b544 → bc237372

  24. 2026-10-04
    Transactions removed

    For the "District Heating Energy Efficiency Project (44000-P146206)", 92 transactions totaling USD 231,268,150.00 were removed and replaced with 92 new transactions totaling USD 231,268,150.00, with money unchanged; this is likely part of a bulk correction.

    • Transactions removed: 92 transactions removed, USD 231.27m

    District Heating Energy Efficiency Project · The World Bank · compare 5c90b544 → bc237372

  25. 2026-10-04
    Transactions removed

    For the project "Pap-Angren Railway (44000-P146328)", 74 transactions totaling USD 84,367,127.00 were removed and replaced with 74 new transactions totaling USD 84,367,127.00, with money unchanged; this is likely part of a bulk correction.

    • Transactions removed: 74 transactions removed, USD 84.37m

    Pap-Angren Railway · The World Bank · compare 5c90b544 → bc237372

  26. 2026-10-04
    Transactions removed

    For the project "Regional Roads Development Project (44000-P146334)", 110 transactions totaling USD 277,074,640.00 were removed and replaced with 110 new transactions totaling USD 277,074,640.00, with money unchanged, as part of a bulk correction.

    • Transactions removed: 110 transactions removed, USD 277.07m

    Regional Roads Development Project · The World Bank · compare 5c90b544 → bc237372

  27. 2026-10-04
    Transactions removed
    +1 more

    For the World Bank project "Modernization of Real Property Registration and Cadastre (44000-P151746)", the budget increased by 39.30% from USD 20,000,000.00 to USD 27,853,527.28, 45 transactions were removed and replaced, and two organizations were updated, as part of a bulk correction across

    • Transactions removed: 45 transactions removed, USD 26.96m
    • Budget changed: Budget USD 20.00m → USD 27.85m (+39.3%)

    Modernization of Real Property Registration and Cadastre · The World Bank · compare 5c90b544 → bc237372

  28. 2026-10-04
    Transactions removed

    For the project "Modernization and Upgrade of Transmission Substations (44000-P156584)", the budget increased by 0.10% from USD 150,000,000.20 to USD 150,185,821.72, alongside updates to 149 transactions, organization identifiers, and receiver names; this is likely part of a bulk correction

    • Transactions removed: 149 transactions removed, USD 264.59m

    Modernization and Upgrade of Transmission Substations · The World Bank · compare 5c90b544 → bc237372

  29. 2026-10-04
    Transactions removed

    For "Medium-Size Cities Integrated Urban Development Project" (44000-P162929), 96 transactions totaling USD 243,976,444.00 were replaced, with money unchanged; this update is part of a bulk correction affecting 18 projects.

    • Transactions removed: 96 transactions removed, USD 243.98m

    Medium-Size Cities Integrated Urban Development Project · The World Bank · compare 5c90b544 → bc237372

  30. 2026-10-04
    Transactions removed
    +1 more

    For the World Bank project "Uzbekistan Reforms for a Sustainable Transformation toward a Market Economy DPO (44000-P166019)", the budget decreased by 50% from USD 2,000,000,000.00 to USD 1,000,000,000.00, alongside transaction and organization updates. This is likely part of a bulk correction

    • Transactions removed: 23 transactions removed, USD 845.92m
    • Budget changed: Budget USD 2.00bn → USD 1.00bn (-50.0%)

    Uzbekistan Reforms for a Sustainable Transformation toward a Market Economy DPO · The World Bank · compare 5c90b544 → bc237372

  31. 2026-10-04
    Transactions removed

    For the World Bank project "Institutional Capacity Building Project (44000-P168180)", 37 transactions totaling 33,699,482.00 USD were replaced with 37 new transactions totaling 33,699,482.00 USD, meaning the total money is unchanged; this is likely part of a bulk correction.

    • Transactions removed: 37 transactions removed, USD 33.70m

    Institutional Capacity Building Project · The World Bank · compare 5c90b544 → bc237372

  32. 2026-10-04
    Transactions removed

    For "Modernizing Uzbekistan National Innovation System Project (44000-P170206)", 42 transactions totaling USD 83,363,845.00 were removed and replaced with 42 new transactions totaling USD 83,363,845.00, while money remained unchanged. This update is likely part of a bulk correction affecting 18 projects.

    • Transactions removed: 42 transactions removed, USD 83.36m

    Modernizing Uzbekistan National Innovation System Project · The World Bank · compare 5c90b544 → bc237372

  33. 2026-10-04
    Transactions removed
    +1 more

    For the World Bank project "Uzbekistan Emergency COVID-19 Response Project (44000-P173827)", the budget increased by 12.50% from USD 20,084,925.00 to USD 22,598,485.24, alongside 51 transactions replaced, multiple organization identifiers updated, and this change formed part of a bulk correction

    • Transactions removed: 51 transactions removed, USD 170.53m
    • Budget changed: Budget USD 20.08m → USD 22.60m (+12.5%)

    Uzbekistan Emergency COVID-19 Response Project · The World Bank · compare 5c90b544 → bc237372

  34. 2026-10-04
    Transactions removed

    For "Clean Energy for Buildings in Uzbekistan (44000-P176060)", 18 transactions totaling USD 148,143,916.00 were removed and replaced with 18 different transactions totaling USD 148,143,916.00, meaning the total money is unchanged; this change is part of a bulk correction across 18 projects.

    • Transactions removed: 18 transactions removed, USD 148.14m

    Clean Energy for Buildings in Uzbekistan · The World Bank · compare 5c90b544 → bc237372

  35. 2026-10-04
    Transactions removed

    For the "Uzbekistan Digital Inclusion Project (44000-P179108)", 10 transactions totaling USD 54,975,302.00 were removed and replaced with 10 new transactions totaling USD 54,975,302.00, keeping the total money unchanged; this is likely part of a bulk correction.

    • Transactions removed: 10 transactions removed, USD 54.98m

    Uzbekistan Digital Inclusion Project · The World Bank · compare 5c90b544 → bc237372

  36. 2026-10-04
    Transactions removed

    For the World Bank project "Connectivity and Transport Sector Improvement Project (44000-P509487)", two transactions totaling USD 200,000,000.00 were removed and replaced with two updated transactions sharing the same total amount and dates (March 31, 2026, and August 31, 2026) but expanding the receiver names, with money unchanged; this

    • Transactions removed: 2 transactions removed, USD 200.00m

    Connectivity and Transport Sector Improvement Project · The World Bank · compare 5c90b544 → bc237372

  37. 2026-10-04
    Transactions removed

    For the project "Access to Finance for Jobs and Growth MPA Phase 1 - Uzbekistan (44000-P511700)", two transactions totaling USD 100,000,000.00 were replaced to update the receiver names, while the total money involved is unchanged; this is likely part of a bulk correction.

    • Transactions removed: 2 transactions removed, USD 100.00m

    Access to Finance for Jobs and Growth MPA Phase 1 - Uzbekistan · The World Bank · compare 5c90b544 → bc237372

  38. 2026-10-04
    Budget changed

    For the "VIETNAM WATER RESOURCES ASSISTANCE (44000-P065898)" project, the budget decreased by 100% from USD 223,728,326.89 to USD 0.00, with multiple expenditure periods removed. This is likely part of a bulk correction affecting 94 projects in the same file update.

    • Budget changed: Budget USD 223.73m → USD 0 (-100.0%)

    VIETNAM WATER RESOURCES ASSISTANCE · The World Bank · compare 626a3077 → e387503d

  39. 2026-10-04
    Budget changed

    For the "Forest Sector Development Project (44000-P066051)", the budget decreased by 100% from USD 34,270,083.96 to USD 0.00; this is likely part of a bulk correction affecting multiple projects.

    • Budget changed: Budget USD 34.27m → USD 0 (-100.0%)

    Forest Sector Development Project · The World Bank · compare 626a3077 → e387503d

  40. 2026-10-04
    Budget changed

    For the project "System Efficiency Improvement, Equitization & Renewables Project (44000-P066396)", the total budget decreased by 100% from USD 236,250,001.19 to USD 0.00; this change is likely part of a bulk correction affecting multiple projects.

    • Budget changed: Budget USD 236.25m → USD 0 (-100.0%)

    System Efficiency Improvement, Equitization & Renewables Project · The World Bank · compare 626a3077 → e387503d

  41. 2026-10-04
    Transactions removed
    +1 more

    For the World Bank project "URBAN UPGRADING PROJECT (44000-P070197)", the budget decreased by 100.00% from USD 213,222,714.57 to USD 0.00, while 336 transactions totaling USD 562,782,992.00 were removed and replaced with an identical set of

    • Transactions removed: 336 transactions removed, USD 562.78m
    • Budget changed: Budget USD 213.22m → USD 0 (-100.0%)

    URBAN UPGRADING PROJECT · The World Bank · compare 626a3077 → e387503d

  42. 2026-10-04
    Budget changed

    For "Natural Disaster Risk Management Project (44000-P073361)", the budget decreased by 100% from USD 84,329,661.00 to USD 0.00; this update is likely part of a bulk correction among 94 projects.

    • Budget changed: Budget USD 84.33m → USD 0 (-100.0%)

    Natural Disaster Risk Management Project · The World Bank · compare 626a3077 → e387503d

  43. 2026-10-04
    Transactions removed
    +1 more

    For the project "Second Rural Energy Project (44000-P074688)", the budget decreased by 100.00% from USD 438,120,909.04 to USD 0.00, and 252 transactions totaling USD 665,172,458.00 were removed and replaced. This is likely part of a bulk correction

    • Transactions removed: 252 transactions removed, USD 665.17m
    • Budget changed: Budget USD 438.12m → USD 0 (-100.0%)

    Second Rural Energy Project · The World Bank · compare 626a3077 → e387503d

  44. 2026-10-04
    Budget changed

    For the project "Public Financial Management Reform Project (44000-P075399)", the budget decreased by 100.00% from USD 64,076,304.33 to USD 0.00; this is likely part of a bulk correction affecting 94 projects in this file update.

    • Budget changed: Budget USD 64.08m → USD 0 (-100.0%)

    Public Financial Management Reform Project · The World Bank · compare 626a3077 → e387503d

  45. 2026-10-04
    Budget changed

    For the World Bank project "Third Rural Transport Project (44000-P075407)", the budget decreased by USD 125,596,705.92 to USD 0.00 and four budget periods were removed, likely as part of a bulk correction across multiple projects.

    • Budget changed: Budget USD 125.60m → USD 0 (-100.0%)

    Third Rural Transport Project · The World Bank · compare 626a3077 → e387503d

  46. 2026-10-04
    Budget changed

    For "VN-Red River Delta Rural Water Supply and Sanitation Project (44000-P077287)", the budget decreased by 100.00% from USD 83,984,164.22 to USD 0.00; this update is likely part of a bulk correction affecting 94 projects.

    • Budget changed: Budget USD 83.98m → USD 0 (-100.0%)

    VN-Red River Delta Rural Water Supply and Sanitation Project · The World Bank · compare 626a3077 → e387503d

  47. 2026-10-04
    Budget changed

    For the "Vietnam - ICT Development (44000-P079344)" project, the budget decreased by 68.50% from USD 128,501,213.54 to USD 40,501,213.54; this change is likely part of a bulk correction affecting multiple projects in the same file update.

    • Budget changed: Budget USD 128.50m → USD 40.50m (-68.5%)

    Vietnam - ICT Development · The World Bank · compare 626a3077 → e387503d

  48. 2026-10-04
    Transactions removed
    +1 more

    For the project "Coastal Cities Environmental Sanitation Project (44000-P082295)", the budget decreased by 100.00% from USD 161,372,156.10 to USD 0.00, and 282 transactions totaling USD 310,306,795.00 were removed and re-added; this change is part of

    • Transactions removed: 282 transactions removed, USD 310.31m
    • Budget changed: Budget USD 161.37m → USD 0 (-100.0%)

    Coastal Cities Environmental Sanitation Project · The World Bank · compare 626a3077 → e387503d

  49. 2026-10-04
    Budget changed

    For the project "HIV/AIDS Prevention (44000-P082604)", the budget decreased by 100.00% from USD 39,700,000.00 to USD 0.00, which is likely part of a bulk correction across multiple projects in this file update.

    • Budget changed: Budget USD 39.70m → USD 0 (-100.0%)

    HIV/AIDS Prevention · The World Bank · compare 626a3077 → e387503d

  50. 2026-10-04
    Transactions removed
    +1 more

    For the project "Northern Upland Health Support Project (44000-P082672)", the budget decreased by 90.10% from USD 66,588,876.06 to USD 6,612,191.96, and 112 transactions totaling USD 96,983,359.00 were removed and replaced with an

    • Transactions removed: 112 transactions removed, USD 96.98m
    • Budget changed: Budget USD 66.59m → USD 6.61m (-90.1%)

    Northern Upland Health Support Project · The World Bank · compare 626a3077 → e387503d

  51. 2026-10-04
    Budget changed

    For the project "Hanoi Urban Transport Development Project (44000-P083581)", the budget decreased by 61.40% from USD 248,017,020.45 to USD 95,643,317.08; this is likely part of a bulk correction affecting multiple projects in the same file update.

    • Budget changed: Budget USD 248.02m → USD 95.64m (-61.4%)

    Hanoi Urban Transport Development Project · The World Bank · compare 626a3077 → e387503d

  52. 2026-10-04
    Budget changed

    For the "Mekong Delta Transport Infrastructure Development Project (44000-P083588)", the budget decreased by 100% from USD 220,493,816.74 to USD 0.00, likely as part of a bulk correction of 94 projects in this file update.

    • Budget changed: Budget USD 220.49m → USD 0 (-100.0%)

    Mekong Delta Transport Infrastructure Development Project · The World Bank · compare 626a3077 → e387503d

  53. 2026-10-04
    Budget changed

    For the "VN-Trung Son Hydropower Project (44000-P084773)", the budget decreased by 87.10% from USD 590,873,526.20 to USD 76,013,526.20; this change is likely part of a bulk correction affecting 94 projects in the same file update.

    • Budget changed: Budget USD 590.87m → USD 76.01m (-87.1%)

    VN-Trung Son Hydropower Project · The World Bank · compare 626a3077 → e387503d

  54. 2026-10-04
    Budget changed

    For the "Second Transmission and Distribution Project (44000-P084871)", the budget was reduced by 100% from USD 205,000,000.00 to USD 0.00, and this change is likely part of a bulk correction affecting 94 projects in the same file update.

    • Budget changed: Budget USD 205.00m → USD 0 (-100.0%)

    Second Transmission and Distribution Project · The World Bank · compare 626a3077 → e387503d

  55. 2026-10-04
    Budget changed

    For the "Road Safety Project (44000-P085080)", the budget decreased by 74.00% from USD 59,762,116.06 to USD 15,532,116.10, with four periods removed; this is likely part of a bulk correction affecting 94 projects in the same file update.

    • Budget changed: Budget USD 59.76m → USD 15.53m (-74.0%)

    Road Safety Project · The World Bank · compare 626a3077 → e387503d

  56. 2026-10-04
    Budget changed

    For "VN-Priority Infrastructure Investment Project (44000-P086508)", the total budget decreased by 92.90% to USD 11,713,406.26 from USD 164,510,072.92; this is likely part of a bulk correction affecting 94 projects in this file update.

    • Budget changed: Budget USD 164.51m → USD 11.71m (-92.9%)

    VN-Priority Infrastructure Investment Project · The World Bank · compare 626a3077 → e387503d

  57. 2026-10-04
    Budget changed

    For the World Bank project "Financial Sector Modernization and Information Management System (44000-P088759)", the budget decreased by 82.70% from USD 69,159,691.12 to USD 11,969,405.00, likely as part of a bulk correction of 94 projects in the same file update.

    • Budget changed: Budget USD 69.16m → USD 11.97m (-82.7%)

    Financial Sector Modernization and Information Management System · The World Bank · compare 626a3077 → e387503d

  58. 2026-10-04
    Budget changed

    For the project "Vietnam Livestock Competitiveness and Food Safety (44000-P090723)", the budget was reduced by 100.00% from USD 64,105,036.00 to USD 0.00; this update is likely part of a bulk correction involving multiple projects.

    • Budget changed: Budget USD 64.11m → USD 0 (-100.0%)

    Vietnam Livestock Competitiveness and Food Safety · The World Bank · compare 626a3077 → e387503d

  59. 2026-10-04
    Budget changed

    For the "School Education Quality Assurance" project, the budget decreased by 95.10% from USD 133,594,254.48 to USD 6,596,454.48, and four periods were removed; this is likely part of a bulk correction affecting 94 projects in the same file update.

    • Budget changed: Budget USD 133.59m → USD 6.60m (-95.1%)

    School Education Quality Assurance · The World Bank · compare 626a3077 → e387503d

  60. 2026-10-04
    Transactions removed
    +1 more

    For the project "VN-Local Development Investment (LDIFP) (44000-P094055)", the budget decreased by 52.10% from USD 226,680,263.16 to USD 108,683,787.34, 95 transactions totaling USD 233,097,858.00

    • Transactions removed: 95 transactions removed, USD 233.10m
    • Budget changed: Budget USD 226.68m → USD 108.68m (-52.1%)

    VN-Local Development Investment (LDIFP) · The World Bank · compare 626a3077 → e387503d

  61. 2026-10-04
    Budget changed

    For the "Northern Delta Transport Development Project (44000-P095129)", the budget decreased by 100% from USD 168,872,185.70 to USD 0.00, with four periods removed, as part of a bulk correction affecting 94 projects.

    • Budget changed: Budget USD 168.87m → USD 0 (-100.0%)

    Northern Delta Transport Development Project · The World Bank · compare 626a3077 → e387503d

  62. 2026-10-04
    Budget changed

    For the "Central North Region Health Support Project (44000-P095275)", the budget decreased by 92.10% from USD 118,513,343.14 to USD 9,405,650.84, with four budget periods removed. This is likely part of a bulk correction involving 94 projects in the same file update.

    • Budget changed: Budget USD 118.51m → USD 9.41m (-92.1%)

    Central North Region Health Support Project · The World Bank · compare 626a3077 → e387503d

  63. 2026-10-04
    Budget changed

    For the "Land Administration Project (44000-P096418)", the total budget decreased by 78.40% from USD 160,799,198.92 to USD 34,799,198.92 and four time periods were removed; this is likely part of a bulk correction affecting 94 projects in the same file update.

    • Budget changed: Budget USD 160.80m → USD 34.80m (-78.4%)

    Land Administration Project · The World Bank · compare 626a3077 → e387503d

  64. 2026-10-04
    Budget changed

    For the World Bank project "Rural Distribution Project (44000-P099211)", the budget decreased by 79.90% to USD 53,150,931.36 from USD 264,128,264.67, likely as part of a bulk correction affecting multiple projects.

    • Budget changed: Budget USD 264.13m → USD 53.15m (-79.9%)

    Rural Distribution Project · The World Bank · compare 626a3077 → e387503d

  65. 2026-10-04
    Budget changed

    For the project "Tax Administration Modernization Project (44000-P099376)", the total budget decreased by 45.60% from USD 290,201,664.53 to USD 157,969,289.52 and four time periods were removed. This change is likely part of a bulk correction affecting multiple projects in the same file update.

    • Budget changed: Budget USD 290.20m → USD 157.97m (-45.6%)

    Tax Administration Modernization Project · The World Bank · compare 626a3077 → e387503d

  66. 2026-10-04
    Transactions removed
    +1 more

    For the World Bank project "Vietnam Third Rural Finance Project (44000-P100916)", the budget decreased by 99.20% from USD 400,000,000.00 to USD 3,250,248.60 and 87 transactions totaling USD 333,552,722.00 were removed, likely as

    • Transactions removed: 87 transactions removed, USD 333.55m
    • Budget changed: Budget USD 400.00m → USD 3.25m (-99.2%)

    Vietnam Third Rural Finance Project · The World Bank · compare 626a3077 → e387503d

  67. 2026-10-04
    Budget changed

    For the project "VN-Avian & Human Influenza Control &Prep (44000-P101608)", the budget decreased by 100% from USD 22,805,488.86 to USD 0.00 and two periods were removed, which is likely part of a bulk correction of 94 projects in this file update.

    • Budget changed: Budget USD 22.81m → USD 0 (-100.0%)

    VN-Avian & Human Influenza Control &Prep · The World Bank · compare 626a3077 → e387503d

  68. 2026-10-04
    Budget changed

    For the project "Vietnam Renewable Energy Development Project (44000-P103238)", the budget decreased by 95.10% from USD 212,470,291.16 to USD 10,470,291.16 and four periods were removed. This is likely part of a bulk correction, as this project is one of 94 projects with material changes

    • Budget changed: Budget USD 212.47m → USD 10.47m (-95.1%)

    Vietnam Renewable Energy Development Project · The World Bank · compare 626a3077 → e387503d

  69. 2026-10-04
    Budget changed

    For the project "Ho Chi Minh City Investment Fund for Urban Development Project (44000-P104848)", the budget decreased by 93.70% from USD 50,310,710.39 to USD 3,181,430.32 and four disbursement periods were removed. This is likely part of a bulk correction.

    • Budget changed: Budget USD 50.31m → USD 3.18m (-93.7%)

    Ho Chi Minh City Investment Fund for Urban Development Project · The World Bank · compare 626a3077 → e387503d

  70. 2026-10-04
    Budget changed

    For the World Bank project "Da Nang-Quang Ngai Expressway Development Project (44000-P106235)", the budget decreased by 51.30% from USD 1,422,527,064.21 to USD 692,360,397.54, removing four budget periods. This is likely part of a bulk correction involving 94

    • Budget changed: Budget USD 1.42bn → USD 692.36m (-51.3%)

    Da Nang-Quang Ngai Expressway Development Project · The World Bank · compare 626a3077 → e387503d

  71. 2026-10-04
    Budget changed

    For the project "VN - Agriculture Competitiveness Project (44000-P108885)", the total budget decreased by 88.70% to USD 10,431,967.02 from USD 92,423,111.50; this is likely part of a bulk correction affecting multiple projects in this file update.

    • Budget changed: Budget USD 92.42m → USD 10.43m (-88.7%)

    VN - Agriculture Competitiveness Project · The World Bank · compare 626a3077 → e387503d

  72. 2026-10-04
    Budget changed

    For the World Bank project "Vietnam New Model University Project (44000-P110693)", the total budget decreased by 54.70% from USD 138,238,897.24 to USD 62,572,230.58; this is likely part of a bulk correction affecting 94 projects in the same file update.

    • Budget changed: Budget USD 138.24m → USD 62.57m (-54.7%)

    Vietnam New Model University Project · The World Bank · compare 626a3077 → e387503d

  73. 2026-10-04
    Budget changed

    For the World Bank project "VIETNAM: Haiphong Urban Transport Project (44000-P111548)", the budget decreased by 79.60% from USD 222,008,683.42 to USD 45,378,683.42, likely as part of a bulk correction affecting 94 projects in this file update.

    • Budget changed: Budget USD 222.01m → USD 45.38m (-79.6%)

    VIETNAM: Haiphong Urban Transport Project · The World Bank · compare 626a3077 → e387503d

  74. 2026-10-04
    Transactions removed
    +1 more

    For "Vietnam Industrial Pollution Management Project (44000-P113151)", the budget decreased by 57.20% from USD 128,037,511.86 to USD 54,787,511.86, while 76 transactions totaling USD 35,008,646.00 were removed and replaced with an equivalent set

    • Transactions removed: 76 transactions removed, USD 35.01m
    • Budget changed: Budget USD 128.04m → USD 54.79m (-57.2%)

    Vietnam Industrial Pollution Management Project · The World Bank · compare 626a3077 → e387503d

  75. 2026-10-04
    Budget changed

    For the "Second Northern Mountains Poverty Reduction Project (44000-P113493)", the budget decreased by 100% from USD 270,000,000.00 to USD 0.00 and multiple periods were removed; this is likely part of a bulk correction affecting 94 projects.

    • Budget changed: Budget USD 270.00m → USD 0 (-100.0%)

    Second Northern Mountains Poverty Reduction Project · The World Bank · compare 626a3077 → e387503d

  76. 2026-10-04
    Budget changed

    For the "Mekong Delta Region Urban Upgrading Project (44000-P113904)", the budget decreased by 81.10% from USD 360,027,631.10 to USD 68,027,631.10. This is likely part of a bulk correction, as it is one of 94 projects with material changes in the same

    • Budget changed: Budget USD 360.03m → USD 68.03m (-81.1%)

    Mekong Delta Region Urban Upgrading Project · The World Bank · compare 626a3077 → e387503d

  77. 2026-10-04
    Transactions removed
    +1 more

    For "VN - Mekong Delta Water Management for Rural Dev (44000-P113949)", the budget increased from USD 261.66 to USD 53,291,586.44, 85 transactions totaling USD 239,978,861.00 were removed and replaced with 85 new transactions, and organizations were updated. This is likely part

    • Transactions removed: 85 transactions removed, USD 239.98m
    • Budget changed: Budget USD 262 → USD 53.29m (+20366630.3%)

    VN - Mekong Delta Water Management for Rural Dev · The World Bank · compare 626a3077 → e387503d

Older changes