Central African Republic – Feasibility Studies for the Boali III Hydropower Plant

46002-P-CF-F00-004

XDR 1.00mdeclared budget
—disbursed and spent, 0 of 1 transactions
Pipelinestatus
30 Sept 2028planned end, was 30 Jun 2027

Budget over time

— declared budget (XDR)   - - disbursed and spent   ○ value changed
Reporting organisation
African Development Bank
Start
30 Jul 2026
Countries
Central African Republic
Sectors
Energy sector policy, planning and administration (23111)
Funded by
Transition Support Facility
Participating
Transition Support Facility (funding); Ministry of finance (implementing)
Versions seen
2 since 26 Sept 2026 · last checked 2026-09-30 02:16 UTC

Changes

  1. 2026-09-29
    Dates changed

    In the project "Central African Republic – Feasibility Studies for the Boali III Hydropower Plant (46002-P-CF-F00-004)", the planned end date was changed from 2027-06-30 to 2028-09-30, and the money is unchanged.

    • Dates changed: planned end 2027-06-30 → 2028-09-30

    Central African Republic – Feasibility Studies for the Boali III Hydropower Plant · compare 5905bf15 → d0e95204

Budgets

PeriodTypeValueRecord
2026-07-30 → 2026-10-30originalXDR 125kcurrent
2026-10-30 → 2027-01-30originalXDR 125kcurrent
2027-01-30 → 2027-04-30originalXDR 125kcurrent
2027-04-30 → 2027-07-30originalXDR 125kcurrent
2027-07-30 → 2027-10-30originalXDR 125kcurrent
2027-10-30 → 2028-01-30originalXDR 125kcurrent
2028-01-30 → 2028-04-30originalXDR 125kcurrent
2028-04-30 → 2028-09-30originalXDR 125kcurrent

Transactions

DateTypeValueToNoteRecord
2026-03-26Outgoing commitmentXDR 1.00mGOUVERNEMENT DE CENTRAFRIQUE