Mozambique - Mueda-Negomano Road Project - Phase I

46002-P-MZ-D00-007

XDR 53.52mdeclared budget
XDR 29.27mdisbursed and spent, 72 of 96 transactions
Implementationstatus
31 Dec 2029planned end

Budget over time

— declared budget (XDR)   - - disbursed and spent   ○ value changed
Reporting organisation
African Development Bank
Start
02 Feb 2017
Countries
Mozambique
Sectors
Public transport services (21012)
Funded by
African Development Fund
Participating
Government Of Mozambique (extending); African Development Fund (funding); National Roads Administration (ANE) (implementing)
Versions seen
2 since 26 Sept 2026 · last checked 2026-09-30 02:16 UTC

Changes

  1. 2026-09-29
    Transactions removed
    +1 more

    For the "Mozambique - Mueda-Negomano Road Project - Phase I" project, transactions were updated to add a new disbursement of 101,708.62 XDR on August 15, 2026, and replace the previous 51,280,000.00 XDR transaction from February 2, 2017, with an equivalent new transaction.

    • Transactions removed: 1 transaction removed, XDR 51.28m
    • Transactions added: 2 transactions added, XDR 51.38m

    Mozambique - Mueda-Negomano Road Project - Phase I · compare 3632aa75 → 745a2dc9

Budgets

PeriodTypeValueRecord
2017-02-02 → 2017-05-02originalXDR 1.05mcurrent
2017-05-02 → 2017-08-02originalXDR 1.05mcurrent
2017-08-02 → 2017-11-02originalXDR 1.05mcurrent
2017-11-02 → 2018-02-02originalXDR 1.05mcurrent
2018-02-02 → 2018-05-02originalXDR 1.05mcurrent
2018-05-02 → 2018-08-02originalXDR 1.05mcurrent
2018-08-02 → 2018-11-02originalXDR 1.05mcurrent
2018-11-02 → 2019-02-02originalXDR 1.05mcurrent
2019-02-02 → 2019-05-02originalXDR 1.05mcurrent
2019-05-02 → 2019-08-02originalXDR 1.05mcurrent
2019-08-02 → 2019-11-02originalXDR 1.05mcurrent
2019-11-02 → 2020-02-02originalXDR 1.05mcurrent
2020-02-02 → 2020-05-02originalXDR 1.05mcurrent
2020-05-02 → 2020-08-02originalXDR 1.05mcurrent
2020-08-02 → 2020-11-02originalXDR 1.05mcurrent
2020-11-02 → 2021-02-02originalXDR 1.05mcurrent
2021-02-02 → 2021-05-02originalXDR 1.05mcurrent
2021-05-02 → 2021-08-02originalXDR 1.05mcurrent
2021-08-02 → 2021-11-02originalXDR 1.05mcurrent
2021-11-02 → 2022-02-02originalXDR 1.05mcurrent
2022-02-02 → 2022-05-02originalXDR 1.05mcurrent
2022-05-02 → 2022-08-02originalXDR 1.05mcurrent
2022-08-02 → 2022-11-02originalXDR 1.05mcurrent
2022-11-02 → 2023-02-02originalXDR 1.05mcurrent
2023-02-02 → 2023-05-02originalXDR 1.05mcurrent
2023-05-02 → 2023-08-02originalXDR 1.05mcurrent
2023-08-02 → 2023-11-02originalXDR 1.05mcurrent
2023-11-02 → 2024-02-02originalXDR 1.05mcurrent
2024-02-02 → 2024-05-02originalXDR 1.05mcurrent
2024-05-02 → 2024-08-02originalXDR 1.05mcurrent
2024-08-02 → 2024-11-02originalXDR 1.05mcurrent
2024-11-02 → 2025-02-02originalXDR 1.05mcurrent
2025-02-02 → 2025-05-02originalXDR 1.05mcurrent
2025-05-02 → 2025-08-02originalXDR 1.05mcurrent
2025-08-02 → 2025-11-02originalXDR 1.05mcurrent
2025-11-02 → 2026-02-02originalXDR 1.05mcurrent
2026-02-02 → 2026-05-02originalXDR 1.05mcurrent
2026-05-02 → 2026-08-02originalXDR 1.05mcurrent
2026-08-02 → 2026-11-02originalXDR 1.05mcurrent
2026-11-02 → 2027-02-02originalXDR 1.05mcurrent
2027-02-02 → 2027-05-02originalXDR 1.05mcurrent
2027-05-02 → 2027-08-02originalXDR 1.05mcurrent
2027-08-02 → 2027-11-02originalXDR 1.05mcurrent
2027-11-02 → 2028-02-02originalXDR 1.05mcurrent
2028-02-02 → 2028-05-02originalXDR 1.05mcurrent
2028-05-02 → 2028-08-02originalXDR 1.05mcurrent
2028-08-02 → 2028-11-02originalXDR 1.05mcurrent
2028-11-02 → 2029-02-02originalXDR 1.05mcurrent
2029-02-02 → 2029-05-02originalXDR 1.05mcurrent
2029-05-02 → 2029-08-02originalXDR 1.05mcurrent
2029-08-02 → 2029-12-31originalXDR 1.05mcurrent

Transactions

DateTypeValueToNoteRecord
2017-02-02Outgoing commitmentXDR 51.28mGovernement of Mozambiquenew
2018-05-31DisbursementXDR 8,902National Roads Administration (ANE)Total Disbursement in May of 2018
2018-08-31DisbursementXDR 12kNational Roads Administration (ANE)Total Disbursement in August of 2018
2019-01-31DisbursementXDR 4.19mNational Roads Administration (ANE)Total Disbursement in January of 2019
2019-05-31DisbursementXDR 130kNational Roads Administration (ANE)Total Disbursement in May of 2019
2019-07-31DisbursementXDR 72kNational Roads Administration (ANE)Total Disbursement in July of 2019
2019-09-30DisbursementXDR 41kNational Roads Administration (ANE)Total Disbursement in September of 2019
2019-10-31DisbursementXDR 664kNational Roads Administration (ANE)Total Disbursement in October of 2019
2019-11-30DisbursementXDR 330kNational Roads Administration (ANE)Total Disbursement in November of 2019
2019-12-31DisbursementXDR 760kNational Roads Administration (ANE)Total Disbursement in December of 2019
2020-01-31DisbursementXDR 11kNational Roads Administration (ANE)Total Disbursement in January of 2020
2020-02-29DisbursementXDR 741kNational Roads Administration (ANE)Total Disbursement in February of 2020
2020-03-31DisbursementXDR 229kNational Roads Administration (ANE)Total Disbursement in March of 2020
2020-05-15DisbursementXDR 7,930National Roads Administration (ANE)Total Disbursement in May of 2020
2020-07-15DisbursementXDR 28kNational Roads Administration (ANE)Total Disbursement in July of 2020
2020-08-15DisbursementXDR 11kNational Roads Administration (ANE)Total Disbursement in August of 2020
2020-09-30DisbursementXDR 49kNational Roads Administration (ANE)Total Disbursement in September of 2020
2020-10-15DisbursementXDR 18kNational Roads Administration (ANE)Total Disbursement in October of 2020
2020-10-31DisbursementXDR 853kNational Roads Administration (ANE)Total Disbursement in October of 2020
2020-12-31DisbursementXDR 694kNational Roads Administration (ANE)Total Disbursement in December of 2020
2021-01-31DisbursementXDR 719kNational Roads Administration (ANE)Total Disbursement in January of 2021
2021-04-15DisbursementXDR 56kNational Roads Administration (ANE)Total Disbursement in April of 2021
2021-04-30DisbursementXDR 938kNational Roads Administration (ANE)Total Disbursement in April of 2021
2021-05-31DisbursementXDR 705kNational Roads Administration (ANE)Total Disbursement in May of 2021
2021-06-15DisbursementXDR 24kNational Roads Administration (ANE)Total Disbursement in June of 2021
2021-07-31DisbursementXDR 548kNational Roads Administration (ANE)Total Disbursement in July of 2021
2021-08-15DisbursementXDR 635kNational Roads Administration (ANE)Total Disbursement in August of 2021
2021-09-15DisbursementXDR 30kNational Roads Administration (ANE)Total Disbursement in September of 2021
2021-10-15DisbursementXDR 899kNational Roads Administration (ANE)Total Disbursement in October of 2021
2021-11-30DisbursementXDR 711kNational Roads Administration (ANE)Total Disbursement in November of 2021
2021-12-31DisbursementXDR 1.53mNational Roads Administration (ANE)Total Disbursement in December of 2021
2022-01-15DisbursementXDR 958kNational Roads Administration (ANE)Total Disbursement in January of 2022
2022-02-15DisbursementXDR 47kNational Roads Administration (ANE)Total Disbursement in February of 2022
2022-02-28DisbursementXDR 68kNational Roads Administration (ANE)Total Disbursement in February of 2022
2022-03-31DisbursementXDR 1.50mNational Roads Administration (ANE)Total Disbursement in March of 2022
2022-04-30DisbursementXDR 31kNational Roads Administration (ANE)Total Disbursement in April of 2022
2022-05-15DisbursementXDR 8,686National Roads Administration (ANE)Total Disbursement in May of 2022
2022-05-31DisbursementXDR 1.68mNational Roads Administration (ANE)Total Disbursement in May of 2022
2022-07-31DisbursementXDR 33kNational Roads Administration (ANE)Total Disbursement in July of 2022
2022-09-30DisbursementXDR 1.03mNational Roads Administration (ANE)Total Disbursement in September of 2022
2022-11-15DisbursementXDR 2.29mNational Roads Administration (ANE)Total Disbursement in November of 2022
2023-02-15DisbursementXDR 44kNational Roads Administration (ANE)Total Disbursement in February of 2023
2023-03-15DisbursementXDR 62kNational Roads Administration (ANE)Total Disbursement in March of 2023
2023-04-30DisbursementXDR 70kNational Roads Administration (ANE)Total Disbursement in April of 2023
2023-06-15DisbursementXDR 1.12mNational Roads Administration (ANE)Total Disbursement in June of 2023
2023-06-30DisbursementXDR 479kNational Roads Administration (ANE)Total Disbursement in June of 2023
2023-07-31DisbursementXDR 5,226National Roads Administration (ANE)Total Disbursement in July of 2023
2023-09-15DisbursementXDR 11kNational Roads Administration (ANE)Total Disbursement in September of 2023
2023-12-15DisbursementXDR 866kNational Roads Administration (ANE)Total Disbursement in December of 2023
2024-01-31DisbursementXDR 541kNational Roads Administration (ANE)Total Disbursement in January of 2024
2024-02-15DisbursementXDR 27kNational Roads Administration (ANE)Total Disbursement in February of 2024
2024-07-15DisbursementXDR 31kNational Roads Administration (ANE)Total Disbursement in July of 2024
2024-08-31DisbursementXDR 823kNational Roads Administration (ANE)Total Disbursement in August of 2024
2024-09-30DisbursementXDR 305kNational Roads Administration (ANE)Total Disbursement in September of 2024
2024-10-15DisbursementXDR 13kNational Roads Administration (ANE)Total Disbursement in October of 2024
2024-12-15DisbursementXDR 68kNational Roads Administration (ANE)Total Disbursement in December of 2024
2025-03-15DisbursementXDR 426kNational Roads Administration (ANE)Total Disbursement in March of 2025
2025-09-30DisbursementXDR 17kNational Roads Administration (ANE)Total Disbursement in September of 2025
2025-10-15DisbursementXDR 57kNational Roads Administration (ANE)Total Disbursement in October of 2025
2025-11-15DisbursementXDR 8,320National Roads Administration (ANE)Total Disbursement in November of 2025
2026-05-15DisbursementXDR 98kNational Roads Administration (ANE)Total Disbursement in May of 2026
2026-08-15DisbursementXDR 102kTotal Disbursement in August of 2026new
2017-11-305XDR 74kAfrican Development FundTotal Interest Repayment in November of 2017
2018-05-315XDR 127kAfrican Development FundTotal Interest Repayment in May of 2018
2018-11-305XDR 129kAfrican Development FundTotal Interest Repayment in November of 2018
2019-05-315XDR 52kAfrican Development FundTotal Interest Repayment in May of 2019
2019-06-305XDR 76kAfrican Development FundTotal Interest Repayment in June of 2019
2019-12-315XDR 129kAfrican Development FundTotal Interest Repayment in December of 2019
2020-01-315XDR 5,553African Development FundTotal Interest Repayment in January of 2020
2020-05-315XDR 135kAfrican Development FundTotal Interest Repayment in May of 2020
2020-11-305XDR 138kAfrican Development FundTotal Interest Repayment in November of 2020
2021-05-315XDR 137kAfrican Development FundTotal Interest Repayment in May of 2021
2021-11-305XDR 143kAfrican Development FundTotal Interest Repayment in November of 2021
2022-05-315XDR 147kGovernement of Mozambique Ministry of FinanceTotal Interest Repayment in May of 2022
2022-11-305XDR 160kGovernement of Mozambique Ministry of FinanceTotal Interest Repayment in November of 2022
2023-06-155XDR 144kGOVERNEMENT OF MOZAMBIQUEMINISTRY OF FINANCETotal Interest Repayment in June of 2023
2023-07-315XDR 14kGOVERNEMENT OF MOZAMBIQUEMINISTRY OF FINANCETotal Interest Repayment in July of 2023
2023-11-305XDR 164kGOVERNEMENT OF MOZAMBIQUEMINISTRY OF FINANCETotal Interest Repayment in November of 2023
2024-06-155XDR 163kGOVERNEMENT OF MOZAMBIQUEMINISTRY OF FINANCETotal Interest Repayment in June of 2024
2024-11-305XDR 165kGovernement of MozambiqueTotal Interest Repayment in November of 2024
2025-05-315XDR 165kGovernement of MozambiqueTotal Interest Repayment in May of 2025
2026-01-155XDR 165kGovernement of MozambiqueTotal Interest Repayment in January of 2026
2026-05-155XDR 163kGovernement of MozambiqueTotal Interest Repayment in May of 2026
2017-02-02Outgoing commitmentXDR 2.24mGovernement of Mozambique - Ministry of Finance
2018-05-31DisbursementXDR 5,064National Roads Administration (ANE)Total Disbursement in May of 2018
2019-05-31DisbursementXDR 2,166National Roads Administration (ANE)Total Disbursement in May of 2019
2021-06-15DisbursementXDR 111kNational Roads Administration (ANE)Total Disbursement in June of 2021
2021-10-31DisbursementXDR 142kNational Roads Administration (ANE)Total Disbursement in October of 2021
2022-06-30DisbursementXDR 157kNational Roads Administration (ANE)Total Disbursement in June of 2022
2022-11-30DisbursementXDR 143kNational Roads Administration (ANE)Total Disbursement in November of 2022
2023-03-15DisbursementXDR 49kNational Roads Administration (ANE)Total Disbursement in March of 2023
2023-09-15DisbursementXDR 86kNational Roads Administration (ANE)Total Disbursement in September of 2023
2024-12-15DisbursementXDR 74kNational Roads Administration (ANE)Total Disbursement in December of 2024
2026-01-15DisbursementXDR 12kNational Roads Administration (ANE)Total Disbursement in January of 2026
2026-05-15DisbursementXDR 32kNational Roads Administration (ANE)Total Disbursement in May of 2026
2017-02-02Outgoing commitmentXDR 5.90m
2017-02-02Outgoing commitmentXDR 51.28mGovernement of Mozambique - Ministry of Financeremoved