New Zealand - Ministry of Foreign Affairs and Trade - New Zealand Aid Programme / mfat-iati-papua-new-guinea
Redevelopment of Lae Main Market
NZ-1-ACT-0A12679
NZD 5.00mdeclared budget
NZD 4.21mdisbursed and spent, 4 of 9 transactions
Implementationstatus
29 Oct 2027planned end, was 29 Feb 2028
Budget over time
- Reporting organisation
- New Zealand Ministry of Foreign Affairs and Trade
- Start
- 17 Apr 2017
- Countries
- Papua New Guinea 100.00%
- Sectors
- Agricultural services (31191) 100.00%
- Funded by
- New Zealand Ministry of Foreign Affairs and Trade
- Participating
- New Zealand Ministry of Foreign Affairs and Trade (funding); New Zealand Ministry of Foreign Affairs and Trade (accountable)
- Versions seen
- 2 since 26 Sept 2026 · last checked 2026-10-04 04:22 UTC
Changes
- 2026-10-01Dates changed+1 more
planned end 2028-02-29 → 2027-10-29
- Transactions added: 2 transactions added, NZD 0
Redevelopment of Lae Main Market · compare 7d88b38a → c98be1e6
Budgets
| Period | Type | Value | Record |
|---|---|---|---|
| 2026-07-01 → 2026-09-30 | original | NZD 5.00m | current |
Transactions
| Date | Type | Value | To | Note | Record |
|---|---|---|---|---|---|
| 2017-06-30 | Expenditure | NZD 35k | Pending Approval | Expenditure incurred in financial year | |
| 2017-09-06 | Expenditure | NZD 126k | Pending Approval | Expenditure incurred in financial year | |
| 2017-12-20 | Expenditure | NZD 46k | Pending Approval | Expenditure incurred in financial year | |
| 2026-04-07 | Outgoing commitment | NZD 5.00m | Pending Approval | Expenditure committed in financial year | |
| 2026-04-08 | Expenditure | NZD 4.00m | Pending Approval | Expenditure incurred in financial year | |
| 2026-08-03 | Outgoing commitment | NZD -5.00m | Pending Approval | Expenditure committed in financial year | |
| 2026-08-03 | Outgoing commitment | NZD 5.00m | Pending Approval | Expenditure committed in financial year | |
| 2026-08-12 | Outgoing commitment | NZD -5.00m | Pending Approval | Expenditure committed in financial year | new |
| 2026-08-12 | Outgoing commitment | NZD 5.00m | Pending Approval | Expenditure committed in financial year | new |
Struck-through rows were in the previous version, last seen 2026-09-30 02:24 UTC, and are not in the current file.