OpenAid Ledger

United Nations Development Programme (UNDP) / undp-cod

Programme Energie-Fonaredd

XM-DAC-41114-OUTPUT-00113647

USD 19.45mdeclared budget
USD 13.10mdisbursed and spent, 50 of 52 transactions
Implementationstatus
31 Dec 2026planned end

Budget over time

— declared budget (USD)   - - disbursed and spent   ○ value changed
Reporting organisation
United Nations Development Programme
Start
26 Dec 2018
Countries
Congo - Kinshasa
Sectors
Business development services (25030) 11.11%; Hydro-electric power plants (23220) 11.11%; Energy generation, renewable sources - multiple technologies (23210) 11.11%; Energy conservation and demand-side efficiency (23183) 11.11%; Energy education/training (23181) 11.11%; Energy sector policy, planning and administration (23111) 11.11%; Communications policy, planning and administration (22011) 11.11%; Public sector policy and administrative management (15110) 11.11%; Education policy and administrative management (11110) 11.12%; 9.4 · SDG target 6.25%; 9.3 · SDG target 6.25%; 9.1 · SDG target 6.25%; 8.3 · SDG target 6.25%; 8.1 · SDG target 6.25%; 7.a · SDG target 6.25%; 7.2 · SDG target 6.25%; 7.1 · SDG target 6.25%; 4.7 · SDG target 6.25%; 17.17 · SDG target 6.25%; 17.16 · SDG target 6.25%; 17.10 · SDG target 6.25%; 17.1 · SDG target 6.25%; 15.2 · SDG target 6.25%; 13.3 · SDG target 6.25%; 13.2 · SDG target 6.25%; 21 · publisher's own 100.00%
Funded by
UNITED NATIONS DEVELOPMENT PROGRAMME; MPTF-Cntrl African Forest init
Participating
United Nations Development Programme (implementing); UNITED NATIONS DEVELOPMENT PROGRAMME (funding); MPTF-Cntrl African Forest init (funding)
Versions seen
3 since 26 Sept 2026 · last checked 2026-10-10 02:27 UTC

Changes

  1. 2026-10-08
    Transaction rewritten
    +1 more

    In the project "Programme Energie-Fonaredd (XM-DAC-41114-OUTPUT-00113647)", transactions totaling USD 12,807,920.00 were redated to span between August 31, 2026, and September 30, 2026, and additional transactions increased by 23.20% to USD 82,

    • Transaction rewritten: 1 transaction restated as of 2026-10-05: total USD 66,576 → USD 82,035 (+23.2%)
    • Transaction rewritten: 1 transaction re-dated (2026-08-31 → 2026-09-30), USD 12,807,920 unchanged

    Programme Energie-Fonaredd · compare 3b7ae417 → e0feefd6

  2. 2026-10-01
    Transaction rewritten

    In project "Programme Energie-Fonaredd (XM-DAC-41114-OUTPUT-00113647)", a transaction was restated with a 10.10% increase to USD 66,576.00 and its date moved from 2026-09-21 to 2026-09-28, likely as part of a bulk correction.

    • Transaction rewritten: 1 transaction restated as of 2026-09-28: total USD 60,492 → USD 66,576 (+10.1%)

    Programme Energie-Fonaredd · compare 1d1957a5 → 3b7ae417

Budgets

PeriodTypeValueRecord
2026-01-01 → 2026-12-31revisedUSD 961kcurrent
2025-01-01 → 2025-12-31revisedUSD 3.20mcurrent
2024-01-01 → 2024-12-31revisedUSD 2.96mcurrent
2023-01-01 → 2023-12-31revisedUSD 2.83mcurrent
2022-01-01 → 2022-12-31revisedUSD 4.39mcurrent
2021-01-01 → 2021-12-31revisedUSD 3.38mcurrent
2020-01-01 → 2020-12-31revisedUSD 1.39mcurrent
2019-01-01 → 2019-12-31revisedUSD 350kcurrent

Transactions

DateTypeValueToNoteRecord
2026-10-05ExpenditureUSD 9,916new
2026-09-30ExpenditureUSD 72knew
2026-08-31ExpenditureUSD 74k
2026-07-31ExpenditureUSD 88k
2026-06-30ExpenditureUSD 245k
2026-05-31ExpenditureUSD 264k
2026-04-30ExpenditureUSD 94k
2026-03-31ExpenditureUSD 277k
2026-02-28ExpenditureUSD 122k
2026-01-31ExpenditureUSD 58k
2025-12-31ExpenditureUSD 371k
2025-11-30ExpenditureUSD 122k
2025-10-31ExpenditureUSD 254k
2025-09-30ExpenditureUSD 85k
2025-08-31ExpenditureUSD 276k
2025-07-31ExpenditureUSD 297k
2025-06-30ExpenditureUSD 266k
2025-05-31ExpenditureUSD 310k
2025-04-30ExpenditureUSD 126k
2025-03-31ExpenditureUSD 169k
2025-02-28ExpenditureUSD 62k
2025-01-31ExpenditureUSD 67k
2024-12-31ExpenditureUSD 114k
2024-11-30ExpenditureUSD 78k
2024-10-31ExpenditureUSD 220k
2024-09-30ExpenditureUSD 56k
2024-08-31ExpenditureUSD 162k
2024-07-31ExpenditureUSD 94k
2024-06-30ExpenditureUSD 151k
2024-05-31ExpenditureUSD 117k
2024-04-30ExpenditureUSD 192k
2024-03-31ExpenditureUSD 273k
2024-02-29ExpenditureUSD 48k
2024-01-31ExpenditureUSD 368k
2023-12-31ExpenditureUSD 178k
2023-11-30ExpenditureUSD 107k
2023-10-31ExpenditureUSD 147k
2023-09-30ExpenditureUSD 592k
2023-08-31ExpenditureUSD 54k
2023-07-31ExpenditureUSD 303k
2023-06-30ExpenditureUSD 54k
2023-05-31ExpenditureUSD -10k
2023-04-30ExpenditureUSD 99k
2023-03-31ExpenditureUSD 111k
2023-02-28ExpenditureUSD 29k
2023-01-31ExpenditureUSD 19k
2022-12-31ExpenditureUSD 2.65m
2021-12-31ExpenditureUSD 1.71m
2020-12-31ExpenditureUSD 1.20m
2019-12-31ExpenditureUSD 272k
2022-12-31Incoming fundsUSD 3.22mUnited Nations Development Programme
2026-09-30Outgoing commitmentUSD 12.81mUnited Nations Development Programmenew
2026-09-28ExpenditureUSD 67kremoved
2026-08-31Outgoing commitmentUSD 12.81mUnited Nations Development Programmeremoved

Struck-through rows were in the previous version, last seen 2026-10-07 02:28 UTC, and are not in the current file.