United Nations Industrial Development Organization (UNIDO) / unido-activity-nigeria
Mini-grid based on Renewable Energy (Biomass) Sources to augment Rural Electrification - Nigeria
XM-DAC-41123-PROJECT-100260
USD 1.48mdeclared budget
USD 1.48mdisbursed and spent, 445 of 890 transactions
Closedstatus
31 Dec 2021planned end
Budget over time
- Reporting organisation
- United Nations Industrial Development Organization
- Start
- 07 Dec 2011 (planned)
- Countries
- —
- Sectors
- 321 · OECD DAC 3-digit
- Funded by
- GEF - Global Environment Facility; Regular Programme Of Technical Cooperati; Special Resources for Africa
- Participating
- United Nations Industrial Development Organization (implementing); GEF - Global Environment Facility (funding); Regular Programme Of Technical Cooperati (funding); Special Resources for Africa (funding)
- Versions seen
- 2 since 26 Sept 2026 · last checked 2026-10-03 02:36 UTC
Changes
- 2026-10-03Transaction rewritten
Transaction on 2013-05-31 rewritten USD 12,526.18 → USD 12,526.17
Mini-grid based on Renewable Energy (Biomass) Sources to augment Rural Electrification - Nigeria · compare 4033cb0e → 14c33931
Budgets
| Period | Type | Value | Record |
|---|---|---|---|
| 2013-01-01 → 2013-12-31 | original | USD 370k | current |
| 2014-01-01 → 2014-12-31 | original | USD 161k | current |
| 2015-01-01 → 2015-12-31 | original | USD 1.19m | current |
| 2016-01-01 → 2016-12-31 | original | USD 121k | current |
| 2017-01-01 → 2017-12-31 | original | USD 75k | current |
| 2018-01-01 → 2018-12-31 | original | USD 227k | current |
| 2019-01-01 → 2019-12-31 | original | USD 157k | current |
| 2020-01-01 → 2020-12-31 | original | USD 80k | current |
| 2021-01-01 → 2021-12-31 | original | USD -688k | current |
| 2022-01-01 → 2022-12-31 | original | USD 9,590 | current |
| 2023-01-01 → 2023-12-31 | original | USD -119k | current |
| 2024-01-01 → 2024-12-31 | original | USD -107k | current |
| 2025-01-01 → 2025-12-31 | original | USD -58 | current |
Transactions
| Date | Type | Value | To | Note | Record |
|---|---|---|---|---|---|
| 2013-01-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2013-01-31 | Expenditure | USD 28k | OP 4. Capacity development | ||
| 2013-01-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2013-01-31 | Expenditure | USD 28k | OP.3 Policy and finance env strengthened | ||
| 2013-01-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2013-01-31 | Expenditure | USD 47k | OP.2 Demonstration of technology | ||
| 2013-02-28 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2013-02-28 | Expenditure | USD 11k | OP.2 Demonstration of technology | ||
| 2013-02-28 | Incoming funds | USD 0 | 5.2 Monitoring | ||
| 2013-02-28 | Expenditure | USD 0 | 5.2 Monitoring | ||
| 2013-03-31 | Incoming funds | USD -632 | OP.1 Preparatory works completed | ||
| 2013-03-31 | Expenditure | USD 0 | OP.1 Preparatory works completed | ||
| 2013-03-31 | Incoming funds | USD 24k | TBD 2.1 A 5 MW Power Plant Commissioned | ||
| 2013-03-31 | Expenditure | USD 0 | TBD 2.1 A 5 MW Power Plant Commissioned | ||
| 2013-03-31 | Incoming funds | USD 11k | TBD 2.2 Capacity Building | ||
| 2013-03-31 | Expenditure | USD 0 | TBD 2.2 Capacity Building | ||
| 2013-03-31 | Incoming funds | USD 1,161 | TBD 2.3 Lessons Learning | ||
| 2013-03-31 | Expenditure | USD 0 | TBD 2.3 Lessons Learning | ||
| 2013-03-31 | Incoming funds | USD -22k | TBD 4.1 Capacity of distribution company | ||
| 2013-03-31 | Expenditure | USD 0 | TBD 4.1 Capacity of distribution company | ||
| 2013-03-31 | Incoming funds | USD -16k | 5.1 Project Managment | ||
| 2013-03-31 | Expenditure | USD 0 | 5.1 Project Managment | ||
| 2013-03-31 | Incoming funds | USD 2,103 | OP.2 Demonstration of technology | ||
| 2013-03-31 | Expenditure | USD 3,663 | OP.2 Demonstration of technology | ||
| 2013-04-30 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2013-04-30 | Expenditure | USD 23k | OP.2 Demonstration of technology | ||
| 2013-04-30 | Incoming funds | USD 0 | 5.2 Monitoring | ||
| 2013-04-30 | Expenditure | USD 1,143 | 5.2 Monitoring | ||
| 2013-05-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2013-05-31 | Expenditure | USD 2,859 | OP 4. Capacity development | ||
| 2013-05-31 | Incoming funds | USD 0 | TBD 2.1 A 5 MW Power Plant Commissioned | ||
| 2013-05-31 | Expenditure | USD 20 | TBD 2.1 A 5 MW Power Plant Commissioned | ||
| 2013-05-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2013-05-31 | Expenditure | USD 16k | OP.2 Demonstration of technology | ||
| 2013-05-31 | Incoming funds | USD 15k | 5.2 Monitoring | ||
| 2013-05-31 | Expenditure | USD 1,898 | 5.2 Monitoring | ||
| 2013-05-31 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2013-05-31 | Expenditure | USD 13k | OP.1 Preparatory works completed | new | |
| 2013-06-30 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2013-06-30 | Expenditure | USD 1,530 | OP 4. Capacity development | ||
| 2013-06-30 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2013-06-30 | Expenditure | USD 624 | OP.3 Policy and finance env strengthened | ||
| 2013-06-30 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2013-06-30 | Expenditure | USD 1,097 | 5.1 Project Managment | ||
| 2013-06-30 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2013-06-30 | Expenditure | USD 4,886 | OP.2 Demonstration of technology | ||
| 2013-07-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2013-07-31 | Expenditure | USD 1,272 | OP.3 Policy and finance env strengthened | ||
| 2013-07-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2013-07-31 | Expenditure | USD 662 | 5.1 Project Managment | ||
| 2013-07-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2013-07-31 | Expenditure | USD 12k | OP.2 Demonstration of technology | ||
| 2013-07-31 | Incoming funds | USD 0 | TBD 2.1 A 5 MW Power Plant Commissioned | ||
| 2013-07-31 | Expenditure | USD 0 | TBD 2.1 A 5 MW Power Plant Commissioned | ||
| 2013-07-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2013-07-31 | Expenditure | USD -4,389 | OP 4. Capacity development | ||
| 2013-07-31 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2013-07-31 | Expenditure | USD 3,233 | OP.1 Preparatory works completed | ||
| 2013-08-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2013-08-31 | Expenditure | USD 4,673 | OP 4. Capacity development | ||
| 2013-08-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2013-08-31 | Expenditure | USD 8,462 | OP.2 Demonstration of technology | ||
| 2013-08-31 | Incoming funds | USD -10 | 5.2 Monitoring | ||
| 2013-08-31 | Expenditure | USD 0 | 5.2 Monitoring | ||
| 2013-09-30 | Incoming funds | USD 0 | 5.2 Monitoring | ||
| 2013-09-30 | Expenditure | USD -331 | 5.2 Monitoring | ||
| 2013-09-30 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2013-09-30 | Expenditure | USD 3,000 | OP.1 Preparatory works completed | ||
| 2013-09-30 | Incoming funds | USD 8,011 | OP 4. Capacity development | ||
| 2013-09-30 | Expenditure | USD 7,122 | OP 4. Capacity development | ||
| 2013-09-30 | Incoming funds | USD 53k | OP.3 Policy and finance env strengthened | ||
| 2013-09-30 | Expenditure | USD 7,984 | OP.3 Policy and finance env strengthened | ||
| 2013-09-30 | Incoming funds | USD -61k | OP.2 Demonstration of technology | ||
| 2013-09-30 | Expenditure | USD 12k | OP.2 Demonstration of technology | ||
| 2013-10-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2013-10-31 | Expenditure | USD -159 | 5.1 Project Managment | ||
| 2013-10-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2013-10-31 | Expenditure | USD -3,084 | OP.2 Demonstration of technology | ||
| 2013-10-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2013-10-31 | Expenditure | USD -1,206 | OP 4. Capacity development | ||
| 2013-10-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2013-10-31 | Expenditure | USD -241 | OP.3 Policy and finance env strengthened | ||
| 2013-10-31 | Incoming funds | USD 0 | 5.2 Monitoring | ||
| 2013-10-31 | Expenditure | USD -982 | 5.2 Monitoring | ||
| 2013-11-30 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2013-11-30 | Expenditure | USD 3,938 | OP.3 Policy and finance env strengthened | ||
| 2013-11-30 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2013-11-30 | Expenditure | USD 6,357 | OP 4. Capacity development | ||
| 2013-11-30 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2013-11-30 | Expenditure | USD 286 | 5.1 Project Managment | ||
| 2013-11-30 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2013-11-30 | Expenditure | USD -36 | OP.1 Preparatory works completed | ||
| 2013-11-30 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2013-11-30 | Expenditure | USD 140k | OP.2 Demonstration of technology | ||
| 2013-11-30 | Incoming funds | USD 0 | 5.2 Monitoring | ||
| 2013-11-30 | Expenditure | USD 786 | 5.2 Monitoring | ||
| 2013-12-31 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2013-12-31 | Expenditure | USD -2,966 | OP.1 Preparatory works completed | ||
| 2013-12-31 | Incoming funds | USD 0 | TBD 2.1 A 5 MW Power Plant Commissioned | ||
| 2013-12-31 | Expenditure | USD 0 | TBD 2.1 A 5 MW Power Plant Commissioned | ||
| 2013-12-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2013-12-31 | Expenditure | USD -5,644 | OP.2 Demonstration of technology | ||
| 2013-12-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2013-12-31 | Expenditure | USD -3,145 | OP.3 Policy and finance env strengthened | ||
| 2013-12-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2013-12-31 | Expenditure | USD 4 | 5.1 Project Managment | ||
| 2013-12-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2013-12-31 | Expenditure | USD -3,152 | OP 4. Capacity development | ||
| 2014-01-31 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2014-01-31 | Expenditure | USD 3,000 | OP.1 Preparatory works completed | ||
| 2014-01-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-01-31 | Expenditure | USD 36k | OP.2 Demonstration of technology | ||
| 2014-01-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-01-31 | Expenditure | USD 14k | OP.3 Policy and finance env strengthened | ||
| 2014-01-31 | Incoming funds | USD 463 | 5.2 Monitoring | ||
| 2014-01-31 | Expenditure | USD 0 | 5.2 Monitoring | ||
| 2014-01-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2014-01-31 | Expenditure | USD 3,195 | OP 4. Capacity development | ||
| 2014-01-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-01-31 | Expenditure | USD 19k | 5.1 Project Managment | ||
| 2014-02-28 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-02-28 | Expenditure | USD 2,340 | 5.1 Project Managment | ||
| 2014-02-28 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-02-28 | Expenditure | USD 153 | OP.3 Policy and finance env strengthened | ||
| 2014-02-28 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-02-28 | Expenditure | USD 7,605 | OP.2 Demonstration of technology | ||
| 2014-03-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-03-31 | Expenditure | USD -933 | OP.3 Policy and finance env strengthened | ||
| 2014-03-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-03-31 | Expenditure | USD 7 | 5.1 Project Managment | ||
| 2014-03-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2014-03-31 | Expenditure | USD 9,600 | OP 4. Capacity development | ||
| 2014-03-31 | Incoming funds | USD 15k | 5.2 Monitoring | ||
| 2014-03-31 | Expenditure | USD 0 | 5.2 Monitoring | ||
| 2014-03-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-03-31 | Expenditure | USD -2,284 | OP.2 Demonstration of technology | ||
| 2014-04-30 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-04-30 | Expenditure | USD 10k | OP.3 Policy and finance env strengthened | ||
| 2014-04-30 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-04-30 | Expenditure | USD 4,441 | 5.1 Project Managment | ||
| 2014-04-30 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2014-04-30 | Expenditure | USD 3,573 | OP 4. Capacity development | ||
| 2014-04-30 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-04-30 | Expenditure | USD 1,796 | OP.2 Demonstration of technology | ||
| 2014-05-31 | Incoming funds | USD -28k | TBD 4.1 Capacity of distribution company | ||
| 2014-05-31 | Expenditure | USD 0 | TBD 4.1 Capacity of distribution company | ||
| 2014-05-31 | Incoming funds | USD -851k | OP.2 Demonstration of technology | ||
| 2014-05-31 | Expenditure | USD 3,989 | OP.2 Demonstration of technology | ||
| 2014-05-31 | Incoming funds | USD 908k | OP.3 Policy and finance env strengthened | ||
| 2014-05-31 | Expenditure | USD 1,191 | OP.3 Policy and finance env strengthened | ||
| 2014-05-31 | Incoming funds | USD -24k | TBD 2.1 A 5 MW Power Plant Commissioned | ||
| 2014-05-31 | Expenditure | USD 0 | TBD 2.1 A 5 MW Power Plant Commissioned | ||
| 2014-05-31 | Incoming funds | USD 96k | OP.1 Preparatory works completed | ||
| 2014-05-31 | Expenditure | USD 7,315 | OP.1 Preparatory works completed | ||
| 2014-05-31 | Incoming funds | USD -106k | 5.1 Project Managment | ||
| 2014-05-31 | Expenditure | USD 433 | 5.1 Project Managment | ||
| 2014-05-31 | Incoming funds | USD 6,453 | OP 4. Capacity development | ||
| 2014-05-31 | Expenditure | USD 4,922 | OP 4. Capacity development | ||
| 2014-06-30 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-06-30 | Expenditure | USD 912 | OP.3 Policy and finance env strengthened | ||
| 2014-06-30 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-06-30 | Expenditure | USD -60 | 5.1 Project Managment | ||
| 2014-06-30 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-06-30 | Expenditure | USD 4,783 | OP.2 Demonstration of technology | ||
| 2014-07-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2014-07-31 | Expenditure | USD 1,388 | OP 4. Capacity development | ||
| 2014-07-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-07-31 | Expenditure | USD 145 | 5.1 Project Managment | ||
| 2014-07-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-07-31 | Expenditure | USD -0 | OP.3 Policy and finance env strengthened | ||
| 2014-07-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-07-31 | Expenditure | USD 3,331 | OP.2 Demonstration of technology | ||
| 2014-07-31 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2014-07-31 | Expenditure | USD 803 | OP.1 Preparatory works completed | ||
| 2014-08-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2014-08-31 | Expenditure | USD -9 | OP 4. Capacity development | ||
| 2014-08-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-08-31 | Expenditure | USD 423 | OP.2 Demonstration of technology | ||
| 2014-08-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-08-31 | Expenditure | USD -51 | 5.1 Project Managment | ||
| 2014-08-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-08-31 | Expenditure | USD 2 | OP.3 Policy and finance env strengthened | ||
| 2014-08-31 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2014-08-31 | Expenditure | USD 3 | OP.1 Preparatory works completed | ||
| 2014-09-30 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-09-30 | Expenditure | USD -1,250 | OP.2 Demonstration of technology | ||
| 2014-09-30 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-09-30 | Expenditure | USD -64 | 5.1 Project Managment | ||
| 2014-09-30 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-09-30 | Expenditure | USD -18 | OP.3 Policy and finance env strengthened | ||
| 2014-10-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-10-31 | Expenditure | USD 2,842 | OP.2 Demonstration of technology | ||
| 2014-10-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-10-31 | Expenditure | USD -40 | OP.3 Policy and finance env strengthened | ||
| 2014-10-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-10-31 | Expenditure | USD -255 | 5.1 Project Managment | ||
| 2014-10-31 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2014-10-31 | Expenditure | USD 2,550 | OP.1 Preparatory works completed | ||
| 2014-11-30 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-11-30 | Expenditure | USD -633 | 5.1 Project Managment | ||
| 2014-11-30 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2014-11-30 | Expenditure | USD 474 | OP 4. Capacity development | ||
| 2014-11-30 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-11-30 | Expenditure | USD 3,949 | OP.3 Policy and finance env strengthened | ||
| 2014-11-30 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-11-30 | Expenditure | USD 7,220 | OP.2 Demonstration of technology | ||
| 2014-12-31 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2014-12-31 | Expenditure | USD 433 | OP.1 Preparatory works completed | ||
| 2014-12-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2014-12-31 | Expenditure | USD 9 | OP 4. Capacity development | ||
| 2014-12-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2014-12-31 | Expenditure | USD 40 | OP.3 Policy and finance env strengthened | ||
| 2014-12-31 | Incoming funds | USD 0 | 5.2 Monitoring | ||
| 2014-12-31 | Expenditure | USD 1,154 | 5.2 Monitoring | ||
| 2014-12-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2014-12-31 | Expenditure | USD 3,624 | OP.2 Demonstration of technology | ||
| 2014-12-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2014-12-31 | Expenditure | USD 78 | 5.1 Project Managment | ||
| 2015-01-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2015-01-31 | Expenditure | USD 15k | OP 4. Capacity development | ||
| 2015-01-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2015-01-31 | Expenditure | USD 100k | OP.3 Policy and finance env strengthened | ||
| 2015-01-31 | Incoming funds | USD -1,752 | 5.2 Monitoring | ||
| 2015-01-31 | Expenditure | USD 5,058 | 5.2 Monitoring | ||
| 2015-01-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2015-01-31 | Expenditure | USD 934 | OP.2 Demonstration of technology | ||
| 2015-02-28 | Incoming funds | USD 447 | OP 4. Capacity development | ||
| 2015-02-28 | Expenditure | USD -494 | OP 4. Capacity development | ||
| 2015-02-28 | Incoming funds | USD 4,526 | OP.3 Policy and finance env strengthened | ||
| 2015-02-28 | Expenditure | USD 6,850 | OP.3 Policy and finance env strengthened | ||
| 2015-02-28 | Incoming funds | USD 190k | 5.1 Project Managment | ||
| 2015-02-28 | Expenditure | USD 2,538 | 5.1 Project Managment | ||
| 2015-02-28 | Incoming funds | USD -95k | OP.1 Preparatory works completed | ||
| 2015-02-28 | Expenditure | USD 0 | OP.1 Preparatory works completed | ||
| 2015-02-28 | Incoming funds | USD -640 | 5.2 Monitoring | ||
| 2015-02-28 | Expenditure | USD 3,291 | 5.2 Monitoring | ||
| 2015-02-28 | Incoming funds | USD -100k | OP.2 Demonstration of technology | ||
| 2015-02-28 | Expenditure | USD 4,805 | OP.2 Demonstration of technology | ||
| 2015-03-31 | Incoming funds | USD 10k | 5.1 Project Managment | ||
| 2015-03-31 | Expenditure | USD -1,219 | 5.1 Project Managment | ||
| 2015-03-31 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2015-03-31 | Expenditure | USD 10 | OP.1 Preparatory works completed | ||
| 2015-03-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2015-03-31 | Expenditure | USD 2,926 | OP 4. Capacity development | ||
| 2015-03-31 | Incoming funds | USD -10k | OP.2 Demonstration of technology | ||
| 2015-03-31 | Expenditure | USD -8,649 | OP.2 Demonstration of technology | ||
| 2015-03-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2015-03-31 | Expenditure | USD -31k | OP.3 Policy and finance env strengthened | ||
| 2015-04-30 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2015-04-30 | Expenditure | USD -13 | OP.1 Preparatory works completed | ||
| 2015-04-30 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2015-04-30 | Expenditure | USD 4,632 | OP.2 Demonstration of technology | ||
| 2015-04-30 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2015-04-30 | Expenditure | USD -556 | OP.3 Policy and finance env strengthened | ||
| 2015-04-30 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2015-04-30 | Expenditure | USD 21k | 5.1 Project Managment | ||
| 2015-05-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2015-05-31 | Expenditure | USD 156 | OP.2 Demonstration of technology | ||
| 2015-05-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2015-05-31 | Expenditure | USD -663 | OP.3 Policy and finance env strengthened | ||
| 2015-05-31 | Incoming funds | USD 0 | OP.1 Preparatory works completed | ||
| 2015-05-31 | Expenditure | USD -0 | OP.1 Preparatory works completed | ||
| 2015-05-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2015-05-31 | Expenditure | USD -0 | OP 4. Capacity development | ||
| 2015-05-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2015-05-31 | Expenditure | USD 313 | 5.1 Project Managment | ||
| 2015-06-30 | Incoming funds | USD 39k | OP.2 Demonstration of technology | ||
| 2015-06-30 | Expenditure | USD 1,921 | OP.2 Demonstration of technology | ||
| 2015-06-30 | Incoming funds | USD -40k | OP.3 Policy and finance env strengthened | ||
| 2015-06-30 | Expenditure | USD 3,256 | OP.3 Policy and finance env strengthened | ||
| 2015-06-30 | Incoming funds | USD 0 | 5.2 Monitoring | ||
| 2015-06-30 | Expenditure | USD -4,263 | 5.2 Monitoring | ||
| 2015-06-30 | Incoming funds | USD 700 | OP.1 Preparatory works completed | ||
| 2015-06-30 | Expenditure | USD -33 | OP.1 Preparatory works completed | ||
| 2015-06-30 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2015-06-30 | Expenditure | USD -307 | OP 4. Capacity development | ||
| 2015-06-30 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2015-06-30 | Expenditure | USD -33 | 5.1 Project Managment | ||
| 2015-07-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2015-07-31 | Expenditure | USD 6,768 | OP 4. Capacity development | ||
| 2015-07-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2015-07-31 | Expenditure | USD 657 | OP.3 Policy and finance env strengthened | ||
| 2015-07-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2015-07-31 | Expenditure | USD 3,109 | OP.2 Demonstration of technology | ||
| 2015-07-31 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2015-07-31 | Expenditure | USD 69 | 5.1 Project Managment | ||
| 2015-08-31 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2015-08-31 | Expenditure | USD 2,390 | OP.2 Demonstration of technology | ||
| 2015-08-31 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2015-08-31 | Expenditure | USD 41k | OP 4. Capacity development | ||
| 2015-08-31 | Incoming funds | USD 0 | 5.2 Monitoring | ||
| 2015-08-31 | Expenditure | USD -89 | 5.2 Monitoring | ||
| 2015-08-31 | Incoming funds | USD 0 | OP.3 Policy and finance env strengthened | ||
| 2015-08-31 | Expenditure | USD -518 | OP.3 Policy and finance env strengthened | ||
| 2015-09-30 | Incoming funds | USD 0 | OP 4. Capacity development | ||
| 2015-09-30 | Expenditure | USD -2,884 | OP 4. Capacity development | ||
| 2015-09-30 | Incoming funds | USD 0 | OP.2 Demonstration of technology | ||
| 2015-09-30 | Expenditure | USD 487k | OP.2 Demonstration of technology | ||
| 2015-09-30 | Incoming funds | USD 0 | 5.1 Project Managment | ||
| 2015-09-30 | Expenditure | USD -79 | 5.1 Project Managment | ||
| 2013-05-31 | Expenditure | USD 13k | OP.1 Preparatory works completed | removed |
Showing 300 of 890. The API returns all of them.